2.6 Earned Value Management

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

Monitoring enables the project manager and team to identify unplanned impacts on scope, cost, schedule, resource, performance, and value. The project manager must regularly compare the amount of money spent with the budgeted amount and report this information to managers and stakeholders. It is necessary to establish an understanding of how this progress will be measured and reported.

Measuring the actual data against the project plan requires information from the project team. As work on the project progresses, the project manager can update the plan with the actual start and finish dates, actual work, actual and remaining duration, and percent of work complete.

Exhibit 2.9: Budget and Actual Cost
Exhibit 2.10: Earned Value Analysis

Estimation Variances

Variance Analysis is a method for determining the cause and degree of differences between the baseline and actual performance.

The differences between the original and the adjusted estimates are called variances. It is important to track and record these variances and examine their causes. Using the concept of progressive elaboration, variances should become smaller throughout the project. Variances between estimated and actual cost, resources, effort, and duration are normal in any project and occur for several reasons based on the specific project life cycles are summarized below:

Predictive Life Cycle Adaptive Life Cycle
Evolution of requirements. Rough order of magnitude (ROM) variances
The duration of the project One-point estimating variances
Approved change request Relative estimation
Operational problems or changing assumptions Velocity
Faulty estimating
Padding

During the project, analyzing variances and taking corrective actions is an important activity that must be completed by the project team and manager. Taking appropriate corrective actions and updating project plans and documentations are required. All issues should be examined and communicated to relevant stakeholders and any issues should be resolved. Any changes in the budget, schedule, and resources should be identified and communicated to the stakeholders and all corrective actions should be addressed and lessons learned documented.

As you read think of examples of factors that may cause deviations from Project Plans for the following factors and provide reasons:

Factors Reasons for deviations from the Project Plans
Scope
Cost
Schedule
Resources
Performance
Value

Earned Value Analysis (EVA)

Earned Value Analysis (EVA) uses a set of measures associated with scope, schedule, and cost to determine the cost and schedule performance of a project. EVA indicates how much of the budget should have been spent, in view of the amount of work done so far and the baseline cost for the task or resources. The project manager should generate and review status reports on the information of a project. Each team must also prepare and share the progress reports of each project with the stakeholders.

EVA uses “work in progress” to indicate the future of a project. EVA examines actual cost at any period during the progress of a project. This provides project managers greater insight into potential risk areas and allows them to plan with risk mitigation plans based on actual cost, schedule, and other elements of the work.

EVA helps answer many questions about project progress and performance and indicates the performance measurements for costs and schedule.

The table below provides a summary of the key terms, their meanings, and formulae to help calculate EVAs.

Cost Term In Short What is it? Formula
Planned Value PV Sum of estimates for work planned to be done up to the present
Earned Value EV Sum of estimates for work done up to the present
Actual Cost AC Sum of actual costs up to the present
Budget at Completion BAC Total approved budget for the project when the scope of the project is completed (includes contingencies).
Estimate to Complete ETC Budget to complete taking into account work done to date and work remaining – in the context of cost performance ETC = (BAC – EV) / (CPI)
Estimate at Completion EAC Budget at completion considering actual cost incurred. EAC = AC + ETC
Cost Variance CV Difference between earned value and actual cost CV = EV – AC
Cost Performance Index CPI Ratio of Earned Value to Actual Cost CPI = EV/AC
Schedule Variance SV Difference between Earned Value and Planned Value SV= EV – PV
Schedule Performance Index SPI Ratio of Earned Value to Planned Value SPI = EV/PV
Variances and Performance Indices Interpretations
Schedule Variance Cost Variance
Variances are deviations from the expectations – difference between planned and actual progress:

SV=EV-PV

  • Positive value: project is ahead of schedule
  • Zero: project is on-time
  • Negative: project is behind schedule

 

The difference between the earned value and the actual cost is the cost variance:

 CV=EV-AC

  • If positive, you are achieving more than you predicted for the money
  • If zero, you are right on the plan
  • If negative, you are achieving less than you predicted for the money
Schedule Performance Index  Cost Performance Index 
Compares progress on the scope to spending:

SPI = EV/PV

  • SPI less than one indicates the project is behind schedule
  • SPI of one is right on schedule
  • SPI greater than one the project is ahead of schedule

 

Compares the budget spent to date with progress to date:

CPI=EV/AC

  • A value greater than one: under budget
  • Equal to one: on budget
  • Less than one: overspending the budget

 

Example – SeaCo, Inc.

SeaCo, Inc., a media and entertainment company is interested in purchasing and installing a new server. The company estimates an activity of a major project for scalability of company offerings to last a week and a cost $20,000, including hardware, software, and installation. The $20,000 is the baseline budgeted cost of the project which is the budget at completion (BAC). SeaCo, Inc., wants to monitor the progress of this project. It finds out that at the end of the second day of a five-day week, 20 percent of the work is completed and $9,000 has been spent. The planned activity had 30 percent completion at the end of the second day.

Solution – SeaCo, Inc.

Earned value is the most effective technique for providing information on project performance. It communicates scope, schedule, and cost status information to project stakeholders. Earned value is a flexible process that provides timely information on the project’s health. It is important to note that effective use of earned value concepts can provide a competitive edge in successfully delivering projects.

License

Managing Project Costs, Risks, Quality and Procurement Copyright © by Florence Daddey. All Rights Reserved.

Share This Book